What problem may occur if projects are not aligned with corporate business strategy?
The correct answer is D. The project management approaches used may differ. See the full explanation below for the reasoning.
Question
What problem may occur if projects are not aligned with corporate business strategy?
Options
- AThe control of projects may be poor
- BThe outputs may be of poor quality
- CThe objectives of different projects may overlap
- DThe project management approaches used may differ
How the community answered
(36 responses)- A14% (5)
- B6% (2)
- C11% (4)
- D69% (25)