PRINCE2-PRACTITIONER Exam Questions
315 real PRINCE2-PRACTITIONER exam questions with expert-verified answers and explanations. Page 5 of 7.
- Question #243Closing a Project process
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
programme escalationmanage by exceptionclosing a projectproject board authority - Question #244Plans theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
manage by stages principlestage tolerancessix aspects of performancemanagement stages - Question #245PRINCE2 Principles
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
focus on productsstakeholder expectationsproduct deliveryPRINCE2 principles - Question #246Tailoring PRINCE2 to the Project Environment
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
tailoring PRINCE2management stagesstandard course structureproject environment - Question #247Business Case Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
continued business justificationcorporate strategybusiness casePRINCE2 principles - Question #248PRINCE2 Principles
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
lessons learnedteam manager responsibilitieslearn from experienceknowledge management - Question #257PRINCE2 Principles
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
focus on productsproduct definitionPRINCE2 principlesproduction baseline - Question #258Managing Product Delivery Process
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
issue escalationteam manager reportingmanaging product deliverycheckpoint report - Question #259Business Case Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
executive rolecontinued business justificationproject boardbusiness case - Question #260PRINCE2 Principles
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
lessons learnedcontinuous improvementquality opportunitieslearn from experience - Question #261Organization Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
project board compositionsenior user rolestakeholder representationorganization structure - Question #262PRINCE2 Principles
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
solid foundationsstarting up a projectPRINCE2 principlestailoring - Question #263Progress Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
time tolerancesproject constraintsexception managementbusiness objectives - Question #264Risk Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
risk management approachtailoringproject controlsproject environment - Question #265Business Case Theme
The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while th...
incremental deliverybusiness case justificationbenefits realizationoutput delivery - Question #266
During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the...
- Question #267Organization Theme
The project is part of a program to develop more training courses that respond to new legislation. The project manager has requested that project support be made available from the...
project support roleprogram officeorganization structureroles and responsibilities - Question #268Change Theme
As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a r...
change authorityexternal stakeholderschange controlstakeholder management - Question #269Quality Theme
At the end of stage 2, an external consultant responsible for developing the 'e-learning course', was appointed to the project board as a senior supplier. The stage 3 plan identifi...
quality review techniquequestion listquality registerreviewer responsibilities - Question #270Change Theme
ABC has experience of delivering training projects that respond to new legislation. Previous projects have had to change the acceptance criteria, due to further updates being made...
acceptance criteriachange controlinitiation stageprioritization - Question #271
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to sta...
- Question #272Change Theme
A change authority has been appointed for the project. During the development of the 'classroom-based training material', a large number of changes were proposed to the design of t...
MoSCoW techniquechange prioritizationbusiness justificationchange authority - Question #273Risk Theme
During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manage...
risk registerintegrated project registertailoringproject registers - Question #274Risk Theme
The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course'...
risk management procedureplan stepimplement steprisk response - Question #275Change theme
The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay...
change budgetcost tolerancechange controlscope change funding - Question #276
The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to...
- Question #277Progress theme
The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the projec...
stage toleranceexception escalationproject board authoritycontrolling a stage - Question #278Progress theme
The project is part of a program to increase the number of ABC courses that respond to legislation. The program manager has instructed the project manager to deliver the 'e- learni...
highlight reportsprogress controlsPID documentationprogram management - Question #279Starting Up a Project process
During the 'starting up a project' process, the project manager discusses the standard model for course development with the executive. The project manager then assesses how the He...
starting up a projectinitiation stage planproject approachSU process - Question #280Managing Product Delivery process
During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered. What should project...
project assurancework package completionproduct approvalquality checking - Question #281Directing a Project process
The project board has asked user and supplier assurance to review all product descriptions relating to the 'updated corporate quality procedures', prior to authorizing the stage pl...
risk registerdirecting a projectproduct descriptionsstage authorization - Question #283Controlling a Stage process
The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external suppl...
exception reportcheckpoint reportswork package monitoringprogress information - Question #284Managing Product Delivery process
MANAGING PRODUCT DELIVERY Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material...
project assurancework package negotiationquality representativesteam manager role - Question #285Managing Product Delivery process
The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and fi...
work package agreementstage toleranceteam manager authoritymanage product delivery - Question #286Managing a Stage Boundary process
MANAGING A STAGE BOUNDARY The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage bounda...
managing a stage boundarybusiness case updateproject plan actualsstage end activities - Question #288Tailoring PRINCE2 / Organization theme
After preparing the stage 3 plan, the project manager left the company. The project board has decided that, as the stage plan has been agreed, it will not appoint a project manager...
PRINCE2 tailoringrole delegationproject manager absenceteam manager responsibilities - Question #289Closing a Project process
CLOSING A PROJECT The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are...
closing a projectbenefits management approachproduct handoverproject manager role - Question #290Organization theme
The 'capability to provide health and safety training' has been delivered. During the 'closing a project' process, the marketing department sent an e-mail to all key customers remi...
organization themestakeholder communicationclosing a projectPRINCE2 themes - Question #291Closing a Project process
The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capabil...
closure planningstage planning timelineclosing a projectproduct acceptance - Question #303Business Case theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
benefits realizationoutcomes managementbusiness case reviewpost-project - Question #304Closing a Project process
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
lessons reportlessons logclosing a projectknowledge capture - Question #305Organization theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
senior user roleorganization themeproject board compositionuser representation - Question #306Plans theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
management stagesstage boundariesinvestment decision pointsproject controls - Question #307Business Case theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
benefit tolerancecorporate management authorityproject tolerancesbusiness case - Question #308PRINCE2 Principles
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
manage by exceptionPRINCE2 principlesproject assuranceproject board confidence - Question #309Organization Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
programme managementproject boardmulti-organizational governancestakeholder representation - Question #311Plans Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
stakeholder engagementcommunication management approachstakeholder identificationstakeholder messages - Question #312Business Case Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
business casecontinued business justificationproject initiationexecutive accountability - Question #314Plans Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
management levelsteam plandelivering levelwork package - Question #315Organization Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
executive rolecommunication responsibilitiesexternal stakeholdersproject manager responsibilities