nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #271

PRINCE2-PRACTITIONER Question #271: Real Exam Question with Answer & Explanation

The correct answer is C. No, because the risks inherent in the project plan should be assessed, and the plan modified to manage them.. See the full explanation below for the reasoning.

Question

During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan. Is this an appropriate application of the plans theme, and why?

Options

  • AYes, because detailed planning of stage 3 should take place after completion of the stage 2 products.
  • BYes, because risk planning should take place in the stage plan before the risks occur, not in the project plan.
  • CNo, because the risks inherent in the project plan should be assessed, and the plan modified to manage them.
  • DNo, because the risk actions to manage project-level threats should be recorded in the risk register.

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice