PRINCE2-PRACTITIONER · Question #271
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products…
Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #271. The question stem and answer options stay visible for context.
Question
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan. Is this an appropriate application of the plans theme, and why?
Options
- AYes, because detailed planning of stage 3 should take place after completion of the stage 2 products.
- BYes, because risk planning should take place in the stage plan before the risks occur, not in the project plan.
- CNo, because the risks inherent in the project plan should be assessed, and the plan modified to manage them.
- DNo, because the risk actions to manage project-level threats should be recorded in the risk register.
Unlock PRINCE2-PRACTITIONER to see the answer
You've previewed enough free PRINCE2-PRACTITIONER questions. Unlock PRINCE2-PRACTITIONER for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.