PRINCE2-PRACTITIONER · Question #139
PRINCE2-PRACTITIONER Question #139: Real Exam Question with Answer & Explanation
The correct answer is B. Understanding the roles and responsibilities of the Project Management Team. Explanation/Reference:
Question
Which of the following is NOT an objective of Initiating a Project?
Options
- AUnderstanding the scope of what is to be done and the products to be delivered
- BUnderstanding the roles and responsibilities of the Project Management Team
- CUnderstand how quality required will be achieved
- DUnderstand how progress will be monitored and controlled
Explanation
Explanation/Reference: