nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #139

PRINCE2-PRACTITIONER Question #139: Real Exam Question with Answer & Explanation

The correct answer is B. Understanding the roles and responsibilities of the Project Management Team. Explanation/Reference:

Question

Which of the following is NOT an objective of Initiating a Project?

Options

  • AUnderstanding the scope of what is to be done and the products to be delivered
  • BUnderstanding the roles and responsibilities of the Project Management Team
  • CUnderstand how quality required will be achieved
  • DUnderstand how progress will be monitored and controlled

Explanation

Explanation/Reference:

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice