PRINCE2
PRINCE2-PRACTITIONER · Question #191
In which process does the Project Manager ask the Project Board where the authority for making change lies?
The correct answer is B. During Initiating a Project. Explanation/Reference:
Initiating a Project
Question
In which process does the Project Manager ask the Project Board where the authority for making change lies?
Options
- ADuring Starting Up A Project
- BDuring Initiating a Project
- CIn Giving Ad Hoc Direction
- DWhen Authorising a Stage
How the community answered
(43 responses)- A7% (3)
- B72% (31)
- C5% (2)
- D16% (7)
Explanation
Explanation/Reference:
Topics
#Initiating a Project#change authority#Project Board#change control
Community Discussion