Which statement is an appropriate entry for the Initiation Stage Plan?
The correct answer is B. The plan is based on the external outsourcing consultants being available at the start of the initiation stage. Explanation/Reference:
Initiating a Project
Question
Which statement is an appropriate entry for the Initiation Stage Plan?
Options
- AThe Daily Log has been updated with the new risks which were identified while preparing the Initiation Stage Plan.
- BThe plan is based on the external outsourcing consultants being available at the start of the initiation stage.
- CThe initial project cost estimate of ?.5m, will have a tolerance of + ?25k J罚75k.
- DThe project management team will consist of representatives from the IT and Facilities Divisions.
How the community answered
(44 responses)- A2% (1)
- B80% (35)
- C7% (3)
- D11% (5)
Explanation
Explanation/Reference:
Topics
#Initiation Stage Plan#resource planning#stage planning#planning assumptions