During stage 1 the level of performance expected from the service provider was changed. After this change was agreed which of these products will require updating?

The correct answer is B. Project Product Description because this contains details of the expected performance of the project's products. Explanation/Reference:

Quality Theme

Question

During stage 1 the level of performance expected from the service provider was changed. After this change was agreed which of these products will require updating?

Options

  • AProject Brief because this is maintained throughout the project to reflect the customer's quality expectations.
  • BProject Product Description because this contains details of the expected performance of the project's products.
  • CQuality Management Strategy because this is where all of the customer's quality expectations of the project's products should be documented.

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    78% (31)
  • C
    15% (6)

Explanation

Explanation/Reference:

Topics

#Project Product Description#quality expectations#change control#configuration management