PRINCE2-PRACTITIONER · Question #195

What does PRINCE2TM suggest is a direct input to the Project Quality Plan?

The correct answer is D. Customer Quality Expectations. Explanation/Reference:

Quality Theme

Question

What does PRINCE2TM suggest is a direct input to the Project Quality Plan?

Options

  • AISO 9001
  • BStage Quality Plan
  • CThe supplier quality policy
  • DCustomer Quality Expectations

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    5% (2)
  • C
    16% (7)
  • D
    72% (31)

Explanation

Explanation/Reference:

Topics

#Project Quality Plan#Customer Quality Expectations#Quality Theme#quality planning