PRINCE2-PRACTITIONER · Question #195
What does PRINCE2TM suggest is a direct input to the Project Quality Plan?
The correct answer is D. Customer Quality Expectations. Explanation/Reference:
Quality Theme
Question
What does PRINCE2TM suggest is a direct input to the Project Quality Plan?
Options
- AISO 9001
- BStage Quality Plan
- CThe supplier quality policy
- DCustomer Quality Expectations
How the community answered
(43 responses)- A7% (3)
- B5% (2)
- C16% (7)
- D72% (31)
Explanation
Explanation/Reference:
Topics
#Project Quality Plan#Customer Quality Expectations#Quality Theme#quality planning