Closure of the project can only be authorised in which of these processes?

The correct answer is D. Lessons Learned Report. Which report assesses what management processes worked well and what went badly? Explanation/Reference:

Closing a Project

Question

Closure of the project can only be authorised in which of these processes?

Options

  • AFollow-on Action Recommendations
  • BEnd Stage Report
  • CBusiness Case review
  • DLessons Learned Report

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    16% (8)
  • D
    75% (38)

Explanation

Which report assesses what management processes worked well and what went badly? Explanation/Reference:

Topics

#Closing a Project#project closure authorization#Directing a Project#Lessons Learned Report