Closure of the project can only be authorised in which of these processes?
The correct answer is D. Lessons Learned Report. Which report assesses what management processes worked well and what went badly? Explanation/Reference:
Closing a Project
Question
Closure of the project can only be authorised in which of these processes?
Options
- AFollow-on Action Recommendations
- BEnd Stage Report
- CBusiness Case review
- DLessons Learned Report
How the community answered
(51 responses)- A4% (2)
- B6% (3)
- C16% (8)
- D75% (38)
Explanation
Which report assesses what management processes worked well and what went badly? Explanation/Reference: