Which of the following activities is NOT an action of preparing for planned closure?

The correct answer is B. Update the Project Management Team. Explanation/Reference:

Closing a Project

Question

Which of the following activities is NOT an action of preparing for planned closure?

Options

  • AUpdate the project plan with actual
  • BUpdate the Project Management Team
  • CRequest a product status account
  • DConfirm project has delivered what is defined in Project Product Description

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    80% (35)
  • C
    7% (3)
  • D
    11% (5)

Explanation

Explanation/Reference:

Topics

#Closing a Project#planned closure#project closure activities