PRINCE2-PRACTITIONER · Question #182
Which of the following activities is NOT an action of preparing for planned closure?
The correct answer is B. Update the Project Management Team. Explanation/Reference:
Closing a Project
Question
Which of the following activities is NOT an action of preparing for planned closure?
Options
- AUpdate the project plan with actual
- BUpdate the Project Management Team
- CRequest a product status account
- DConfirm project has delivered what is defined in Project Product Description
How the community answered
(44 responses)- A2% (1)
- B80% (35)
- C7% (3)
- D11% (5)
Explanation
Explanation/Reference:
Topics
#Closing a Project#planned closure#project closure activities