PRINCE2-PRACTITIONER · Question #181

Which of the following statements is FALSE regarding the Continued Business Justification?

The correct answer is A. The justification for the project must remain the same throughout the project. Explanation/Reference:

PRINCE2 Principles

Question

Which of the following statements is FALSE regarding the Continued Business Justification?

Options

  • AThe justification for the project must remain the same throughout the project.
  • BThe justification for the project should remain vabd.
  • CThe justification for the project may change.
  • DIf the project is no longer justified it should be stopped.

How the community answered

(27 responses)
  • A
    74% (20)
  • B
    7% (2)
  • C
    15% (4)
  • D
    4% (1)

Explanation

Explanation/Reference:

Topics

#Continued Business Justification#PRINCE2 principles#project justification