PRINCE2
PRINCE2-PRACTITIONER · Question #2
Which of the following statements is NOT correct? The Learn from Experience principle suggests that lessons should be actively sought...
The correct answer is B. When Initiating a Project. Explanation/Reference:
PRINCE2 Principles
Question
Which of the following statements is NOT correct? The Learn from Experience principle suggests that lessons should be actively sought...
Options
- AWhen Starting a Project
- BWhen Initiating a Project
- CAs the project progresses
- DAs the project closes
How the community answered
(26 responses)- A4% (1)
- B77% (20)
- C8% (2)
- D12% (3)
Explanation
Explanation/Reference:
Topics
#learn from experience#project initiation#lessons#PRINCE2 principles