The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
The correct answer is D. Scope, Risk, Benefit. Explanation/Reference:
PRINCE2 Principles
Question
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
Options
- AScope, People & Resources, Benefit
- BScope, Risk, Product
- CRisk, Benefit, Product
- DScope, Risk, Benefit
How the community answered
(46 responses)- A2% (1)
- B11% (5)
- C7% (3)
- D80% (37)