Question

The project is in stage 3. The BuildyBrick construction teams are unsure about using the required environmentally friendly concrete technique. As the team has not used the technique before, the work could take longer than originally planned. The Regeneration Manager has arranged a visit to another site where the technique is being used. Which principle is being applied, and why?

Options

  • ALearn from experience, because a field trip provides an opportunity to learn from others
  • BLearn from experience, because lessons should only be reviewed at project start
  • CManage by exception, because work package time tolerance may be exceeded
  • DManage by exception, because the CEO should resolve the concern

Unlock PRINCE2-PRACTITIONER to see the answer