Which of the following activities could trigger the production of an exception plan?

The correct answer is B. Giving ad hoc direction. Explanation/Reference:

Directing a Project

Question

Which of the following activities could trigger the production of an exception plan?

Options

  • AReview Stage status
  • BGiving ad hoc direction
  • CEscalating a project issue
  • DReport stage end

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    70% (28)
  • C
    5% (2)
  • D
    18% (7)

Explanation

Explanation/Reference:

Topics

#Exception Plan#Directing a Project#ad hoc direction#escalation