PRINCE2-PRACTITIONER · Question #180
Which of the following activities could trigger the production of an exception plan?
The correct answer is B. Giving ad hoc direction. Explanation/Reference:
Directing a Project
Question
Which of the following activities could trigger the production of an exception plan?
Options
- AReview Stage status
- BGiving ad hoc direction
- CEscalating a project issue
- DReport stage end
How the community answered
(40 responses)- A8% (3)
- B70% (28)
- C5% (2)
- D18% (7)
Explanation
Explanation/Reference:
Topics
#Exception Plan#Directing a Project#ad hoc direction#escalation