If Project tolerances were threatened, who needs to be notified?
The correct answer is D. Directing a Project. During which process would the stage tolerances be set? Explanation/Reference:
Directing a Project
Question
If Project tolerances were threatened, who needs to be notified?
Options
- AControlling a Stage
- BInitiating a Project
- CManaging a Stage Boundary
- DDirecting a Project
How the community answered
(25 responses)- A4% (1)
- B8% (2)
- C16% (4)
- D72% (18)
Explanation
During which process would the stage tolerances be set? Explanation/Reference:
Topics
#project tolerance#escalation#Project Board#Directing a Project