PRINCE2-PRACTITIONER · Question #117

If Project tolerances were threatened, who needs to be notified?

The correct answer is D. Directing a Project. During which process would the stage tolerances be set? Explanation/Reference:

Directing a Project

Question

If Project tolerances were threatened, who needs to be notified?

Options

  • AControlling a Stage
  • BInitiating a Project
  • CManaging a Stage Boundary
  • DDirecting a Project

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    16% (4)
  • D
    72% (18)

Explanation

During which process would the stage tolerances be set? Explanation/Reference:

Topics

#project tolerance#escalation#Project Board#Directing a Project