PRINCE2-PRACTITIONER · Question #119

PRINCE2-PRACTITIONER Question #119: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #119. The question stem and answer options stay visible for context.

Question

Which of the following is not a factor to consider when determining the length of a stage?

Options

  • AThe amount of resources available h the short term
  • BHow far ahead you can sensibly plan n detail
  • CThe technical stages within the project
  • DThe amount of risk associated with the project