Who sets the tolerances for a work package?

The correct answer is B. The project manager. Explanation/Reference:

Plans

Question

Who sets the tolerances for a work package?

Options

  • AThe project board
  • BThe project manager
  • CThe team manager
  • DCorporate or programme management

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    70% (30)
  • C
    19% (8)
  • D
    5% (2)

Explanation

Explanation/Reference:

Topics

#work package#tolerances#project manager role#delegating work