Who sets the tolerances for a work package?
The correct answer is B. The project manager. Explanation/Reference:
Plans
Question
Who sets the tolerances for a work package?
Options
- AThe project board
- BThe project manager
- CThe team manager
- DCorporate or programme management
How the community answered
(43 responses)- A7% (3)
- B70% (30)
- C19% (8)
- D5% (2)
Explanation
Explanation/Reference:
Topics
#work package#tolerances#project manager role#delegating work