PRINCE2
PRINCE2-PRACTITIONER · Question #179
Which of the following management products ARE updated as part of Managing a stage boundary? 1. Business Case 2. Benefits Review Plan 3. Configuration Item Records 4. Project Brief
See the full explanation below for the reasoning.
Question
Which of the following management products ARE updated as part of Managing a stage boundary? 1. Business Case 2. Benefits Review Plan 3. Configuration Item Records 4. Project Brief
Options
- A1, 2, 3
- B1, 3, 4
- C1, 2, 4
Community Discussion