When updating the project plan as part of Managing a stage boundary, what else might be updated?

The correct answer is D. Project Initiation Documentation. Explanation/Reference: PID (in particular in particular the business case, project plan, project approaches, project management team structure and role descriptions.

Managing a Stage Boundary

Question

When updating the project plan as part of Managing a stage boundary, what else might be updated?

Options

  • AException Plan
  • BProject Management team
  • CBusiness Case
  • DProject Initiation Documentation

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    14% (3)
  • C
    9% (2)
  • D
    73% (16)

Explanation

Explanation/Reference: PID (in particular in particular the business case, project plan, project approaches, project management team structure and role descriptions.

Topics

#Managing a Stage Boundary#Project Plan#Project Initiation Documentation#stage end