When updating the project plan as part of Managing a stage boundary, what else might be updated?
The correct answer is D. Project Initiation Documentation. Explanation/Reference: PID (in particular in particular the business case, project plan, project approaches, project management team structure and role descriptions.
Managing a Stage Boundary
Question
When updating the project plan as part of Managing a stage boundary, what else might be updated?
Options
- AException Plan
- BProject Management team
- CBusiness Case
- DProject Initiation Documentation
How the community answered
(22 responses)- A5% (1)
- B14% (3)
- C9% (2)
- D73% (16)
Explanation
Explanation/Reference: PID (in particular in particular the business case, project plan, project approaches, project management team structure and role descriptions.