CLOSING A PROJECT The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are being handed over…

The correct answer is C. Project manager. Explanation/Reference:

Closing a Project process

Question

CLOSING A PROJECT The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are being handed over. This check should ensure that it includes appropriate activities to assess whether the actual course sales meet the agreed forecast in the business case. Which role should undertake this review as part of the 'closing a project' process?

Options

  • AProgram management.
  • BProject board.
  • CProject manager.
  • DProject assurance.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    77% (20)
  • D
    12% (3)

Explanation

Explanation/Reference:

Topics

#closing a project#benefits management approach#product handover#project manager role