PRINCE2-PRACTITIONER · Question #288

After preparing the stage 3 plan, the project manager left the company. The project board has decided that, as the stage plan has been agreed, it will not appoint a project manager for stage 3. The…

The correct answer is A. Yes, because work may be delegated to those with the necessary skills, such as a team manager. Explanation/Reference: Although the project manager is responsible for the day-to-day management of the project, team members are responsible for delivering the project's products to an appropriate quality within a specified timescale and cost. Depending on the size and…

Tailoring PRINCE2 / Organization theme

Question

After preparing the stage 3 plan, the project manager left the company. The project board has decided that, as the stage plan has been agreed, it will not appoint a project manager for stage 3. The team managers will report directly to the project board and will prepare highlight reports instead of checkpoint reports. Is this an appropriate tailoring of the roles in the 'managing a stage boundary' process?

Options

  • AYes, because work may be delegated to those with the necessary skills, such as a team manager.
  • BYes, because the team managers should have the information required to prepare highlight reports.
  • CNo, because the reporting in the 'controlling a stage' process should not be changed.
  • DNo, because the team managers should not share the responsibilities of the project manager.

How the community answered

(34 responses)
  • A
    74% (25)
  • B
    15% (5)
  • C
    9% (3)
  • D
    3% (1)

Explanation

Explanation/Reference: Although the project manager is responsible for the day-to-day management of the project, team members are responsible for delivering the project's products to an appropriate quality within a specified timescale and cost. Depending on the size and complexity of the project, the authority and responsibility for planning the creation of certain products and managing a team of specialists to produce those products may be delegated to a team manager.

Topics

#PRINCE2 tailoring#role delegation#project manager absence#team manager responsibilities