PRINCE2-PRACTITIONER · Question #286

PRINCE2-PRACTITIONER Question #286: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #286. The question stem and answer options stay visible for context.

Question

MANAGING A STAGE BOUNDARY The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process. Which action should the project manager undertake as part of the 'update the business case' activity?

Options

  • AInclude the actual time and cost of the work to prepare the 'marketing materials' in the project plan.
  • BEnsure that the team manager for the work package 'delivered pilot courses' is included as a resource.
  • CUpdate the project's business case to show any new key risks that have been identified.
  • DInclude the tolerances for the work package 'delivered pilot courses' in the project plan.

Unlock PRINCE2-PRACTITIONER to see the answer

You've previewed enough free PRINCE2-PRACTITIONER questions. Unlock PRINCE2-PRACTITIONER for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.