MANAGING A STAGE BOUNDARY The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process. Which…
The correct answer is A. Include the actual time and cost of the work to prepare the 'marketing materials' in the project plan. Explanation/Reference: Which action should the project manager carry out as part of the 'update the project plan' activity? Explanation/Reference:
Question
MANAGING A STAGE BOUNDARY The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process. Which action should the project manager undertake as part of the 'update the business case' activity?
Options
- AInclude the actual time and cost of the work to prepare the 'marketing materials' in the project plan.
- BEnsure that the team manager for the work package 'delivered pilot courses' is included as a resource.
- CUpdate the project's business case to show any new key risks that have been identified.
- DInclude the tolerances for the work package 'delivered pilot courses' in the project plan.
How the community answered
(35 responses)- A86% (30)
- B3% (1)
- C3% (1)
- D9% (3)
Explanation
Explanation/Reference: Which action should the project manager carry out as part of the 'update the project plan' activity? Explanation/Reference: