PRINCE2-PRACTITIONER · Question #286

MANAGING A STAGE BOUNDARY The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process. Which…

The correct answer is A. Include the actual time and cost of the work to prepare the 'marketing materials' in the project plan. Explanation/Reference: Which action should the project manager carry out as part of the 'update the project plan' activity? Explanation/Reference:

Managing a Stage Boundary process

Question

MANAGING A STAGE BOUNDARY The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process. Which action should the project manager undertake as part of the 'update the business case' activity?

Options

  • AInclude the actual time and cost of the work to prepare the 'marketing materials' in the project plan.
  • BEnsure that the team manager for the work package 'delivered pilot courses' is included as a resource.
  • CUpdate the project's business case to show any new key risks that have been identified.
  • DInclude the tolerances for the work package 'delivered pilot courses' in the project plan.

How the community answered

(35 responses)
  • A
    86% (30)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)

Explanation

Explanation/Reference: Which action should the project manager carry out as part of the 'update the project plan' activity? Explanation/Reference:

Topics

#managing a stage boundary#business case update#project plan actuals#stage end activities

Community Discussion

No community discussion yet for this question.