nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #285

The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and finds that the…

The correct answer is B. Yes, because the team manager should agree the limits within which the work is to be completed. Explanation/Reference:

Managing Product Delivery process

Question

The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and finds that the expected delivery date is unrealistic. As a result, the project manager agrees an extra two weeks to complete the work package, within the current stage tolerance. The work package is then accepted by the team manager. Is this an appropriate application of the 'manage product delivery' process, and why?

Options

  • AYes, because the team manager should set the time required to complete a work package.
  • BYes, because the team manager should agree the limits within which the work is to be completed.
  • CNo, because the work package, defined by the project manager, should not be changed.
  • DNo, because the use of the stage time tolerance should be authorized by the project board.

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    84% (16)
  • D
    11% (2)

Explanation

Explanation/Reference:

Topics

#work package agreement#stage tolerance#team manager authority#manage product delivery

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice