Question
MANAGING PRODUCT DELIVERY Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable. Which action should the team manager take in response?
Options
- ADiscuss the situation with project assurance.
- BAdvise the project manager of this risk.
- CUpdate the quality register with these concerns.
- DRaise an exception report to the project manager.
Unlock PRINCE2-PRACTITIONER to see the answer
You've previewed enough free PRINCE2-PRACTITIONER questions. Unlock PRINCE2-PRACTITIONER for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.