PRINCE2
PRINCE2-PRACTITIONER · Question #284
MANAGING PRODUCT DELIVERY Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that…
The correct answer is A. Discuss the situation with project assurance. Explanation/Reference:
Managing Product Delivery process
Question
MANAGING PRODUCT DELIVERY Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable. Which action should the team manager take in response?
Options
- ADiscuss the situation with project assurance.
- BAdvise the project manager of this risk.
- CUpdate the quality register with these concerns.
- DRaise an exception report to the project manager.
How the community answered
(15 responses)- A73% (11)
- B13% (2)
- C7% (1)
- D7% (1)
Explanation
Explanation/Reference:
Topics
#project assurance#work package negotiation#quality representatives#team manager role
Community Discussion