MANAGING PRODUCT DELIVERY Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that…

The correct answer is A. Discuss the situation with project assurance. Explanation/Reference:

Managing Product Delivery process

Question

MANAGING PRODUCT DELIVERY Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable. Which action should the team manager take in response?

Options

  • ADiscuss the situation with project assurance.
  • BAdvise the project manager of this risk.
  • CUpdate the quality register with these concerns.
  • DRaise an exception report to the project manager.

How the community answered

(15 responses)
  • A
    73% (11)
  • B
    13% (2)
  • C
    7% (1)
  • D
    7% (1)

Explanation

Explanation/Reference:

Topics

#project assurance#work package negotiation#quality representatives#team manager role