PRINCE2-PRACTITIONER · Question #291
The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide…
The correct answer is C. No, because closure activities should have been planned at the end of stage 3. Explanation/Reference: Here are three statements from the business case for the Health and Safety Project. Under which heading in the business case (A-F) should they be recorded? Choose only one heading for each statement. Each heading can be used once, more than once, or not…
Question
The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'. Is this appropriate, and why?
Exhibits
Options
- AYes, because a plan should be created to measure the number of courses carried out after project closure.
- BYes, because a separate closure stage plan should be created during stage 4.
- CNo, because closure activities should have been planned at the end of stage 3.
- DNo, because user acceptance of the project's products should have taken place throughout the project.
How the community answered
(36 responses)- A3% (1)
- B11% (4)
- C72% (26)
- D14% (5)
Explanation
Explanation/Reference: Here are three statements from the business case for the Health and Safety Project. Under which heading in the business case (A-F) should they be recorded? Choose only one heading for each statement. Each heading can be used once, more than once, or not at all. Select and Place: Explanation/Reference: