nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #291

PRINCE2-PRACTITIONER Question #291: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #291. The question stem and answer options stay visible for context.

Question

The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'. Is this appropriate, and why?

Exhibits

PRINCE2-PRACTITIONER question #291 exhibit 1
PRINCE2-PRACTITIONER question #291 exhibit 2

Options

  • AYes, because a plan should be created to measure the number of courses carried out after project closure.
  • BYes, because a separate closure stage plan should be created during stage 4.
  • CNo, because closure activities should have been planned at the end of stage 3.
  • DNo, because user acceptance of the project's products should have taken place throughout the project.

Unlock PRINCE2-PRACTITIONER to see the answer

You've previewed enough free PRINCE2-PRACTITIONER questions. Unlock PRINCE2-PRACTITIONER for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PRINCE2-PRACTITIONER Practice