PRINCE2
PRINCE2-PRACTITIONER · Question #291
PRINCE2-PRACTITIONER Question #291: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #291. The question stem and answer options stay visible for context.
Question
The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'. Is this appropriate, and why?
Exhibits
Options
- AYes, because a plan should be created to measure the number of courses carried out after project closure.
- BYes, because a separate closure stage plan should be created during stage 4.
- CNo, because closure activities should have been planned at the end of stage 3.
- DNo, because user acceptance of the project's products should have taken place throughout the project.
Unlock PRINCE2-PRACTITIONER to see the answer
You've previewed enough free PRINCE2-PRACTITIONER questions. Unlock PRINCE2-PRACTITIONER for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

