Which principle is supported by the activity Evaluate the Project?
The correct answer is C. Learn from experience. Explanation/Reference:
PRINCE2 Principles
Question
Which principle is supported by the activity Evaluate the Project?
Options
- AContinued Business Justification
- BDefined roles and responsibilities
- CLearn from experience
- DManage by stages
How the community answered
(21 responses)- A5% (1)
- B10% (2)
- C81% (17)
- D5% (1)
Explanation
Explanation/Reference:
Topics
#Closing a Project#Learn from Experience#PRINCE2 principles#project evaluation