PRINCE2-PRACTITIONER · Question #192
Apart from the Issue Log, what else is updated by the lower level process "Examining Project Issues"?
The correct answer is C. Risk Log. Explanation/Reference:
Change Theme
Question
Apart from the Issue Log, what else is updated by the lower level process "Examining Project Issues"?
Options
- ALessons Learned Log
- BBusiness Case
- CRisk Log
- DStage Plan
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- C81% (25)
- D6% (2)
Explanation
Explanation/Reference:
Topics
#Issue management#Risk Log#Examining Project Issues#issue process