PRINCE2-PRACTITIONER · Question #192

Apart from the Issue Log, what else is updated by the lower level process "Examining Project Issues"?

The correct answer is C. Risk Log. Explanation/Reference:

Change Theme

Question

Apart from the Issue Log, what else is updated by the lower level process "Examining Project Issues"?

Options

  • ALessons Learned Log
  • BBusiness Case
  • CRisk Log
  • DStage Plan

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    81% (25)
  • D
    6% (2)

Explanation

Explanation/Reference:

Topics

#Issue management#Risk Log#Examining Project Issues#issue process

Community Discussion

No community discussion yet for this question.