PRINCE2-PRACTITIONER · Question #268

As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on…

The correct answer is B. Yes, because a change authority should consider external stakeholder needs. Explanation/Reference:

Change Theme

Question

As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on the project board. Should their interests be represented within the change authority for the project, and why?

Options

  • AYes, because this will give them a better understanding of the training materials.
  • BYes, because a change authority should consider external stakeholder needs.
  • CNo, because the change authority should be internal to the ABC organization.
  • DNo, because their project board member will be able to agree any required changes.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    82% (23)
  • C
    4% (1)
  • D
    11% (3)

Explanation

Explanation/Reference:

Topics

#change authority#external stakeholders#change control#stakeholder management