PRINCE2-PRACTITIONER · Question #268
As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on…
The correct answer is B. Yes, because a change authority should consider external stakeholder needs. Explanation/Reference:
Change Theme
Question
As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on the project board. Should their interests be represented within the change authority for the project, and why?
Options
- AYes, because this will give them a better understanding of the training materials.
- BYes, because a change authority should consider external stakeholder needs.
- CNo, because the change authority should be internal to the ABC organization.
- DNo, because their project board member will be able to agree any required changes.
How the community answered
(28 responses)- A4% (1)
- B82% (23)
- C4% (1)
- D11% (3)
Explanation
Explanation/Reference:
Topics
#change authority#external stakeholders#change control#stakeholder management