PRINCE2-PRACTITIONER · Question #163

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of ?50k, but was undecided on the Change…

The correct answer is B. Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget. Explanation/Reference:

Change Theme

Question

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of ?50k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?

Options

  • AThe selected service provider to approve and implement all changes.
  • BSenior User(s) and Project Assurance representatives, within the limits of the recommended change budget.
  • CThe Director of Facilities and the Director of Information Technology to approve all changes.

How the community answered

(50 responses)
  • A
    6% (3)
  • B
    84% (42)
  • C
    10% (5)

Explanation

Explanation/Reference:

Topics

#Configuration Management Strategy#Change Authority#change budget#change control