PRINCE2
PRINCE2-PRACTITIONER · Question #163
While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of ?50k, but was undecided on the Change…
The correct answer is B. Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget. Explanation/Reference:
Change Theme
Question
While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of ?50k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?
Options
- AThe selected service provider to approve and implement all changes.
- BSenior User(s) and Project Assurance representatives, within the limits of the recommended change budget.
- CThe Director of Facilities and the Director of Information Technology to approve all changes.
How the community answered
(50 responses)- A6% (3)
- B84% (42)
- C10% (5)
Explanation
Explanation/Reference:
Topics
#Configuration Management Strategy#Change Authority#change budget#change control
Community Discussion
No community discussion yet for this question.