PRINCE2-PRACTITIONER · Question #164
While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management. Which option provides an…
The correct answer is C. Seek relevant organizational standards, then facilitate a workshop to discuss the Quality Management Strategy with Project Assurance. Explanation/Reference:
Quality Theme
Question
While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management. Which option provides an appropriate way for the Project Manager proceed?
Options
- ARecord the development of a corporate quality management system for project management as a prerequisite of the Project Plan.
- BProceed with the project without a Quality Management Strategy and adopt the selected service provider's standards in stage 4.
- CSeek relevant organizational standards, then facilitate a workshop to discuss the Quality Management Strategy with Project Assurance.
How the community answered
(40 responses)- A15% (6)
- B8% (3)
- C78% (31)
Explanation
Explanation/Reference:
Topics
#Quality Management Strategy#corporate standards#Project Assurance#quality system