At the end of stage 2, an external consultant responsible for developing the 'e-learning course', was appointed to the project board as a senior supplier. The stage 3 plan identifies the consultant…

The correct answer is C. No, because possible errors that are found when preparing for a quality review should be documented on a question list. Explanation/Reference:

Quality Theme

Question

At the end of stage 2, an external consultant responsible for developing the 'e-learning course', was appointed to the project board as a senior supplier. The stage 3 plan identifies the consultant as a reviewer of the 'e-learning course'. When preparing for a quality review of the 'e-learning course', the consultant found 15 possible errors. The consultant then documented these possible errors in the quality register. Is this an appropriate activity when preparing for a quality review, and why?

Options

  • AYes, because each team manager should update the quality register as quality review activities are completed.
  • BYes, because the quality reviewers should update the quality register as quality review activities are completed.
  • CNo, because possible errors that are found when preparing for a quality review should be documented on a question list.
  • DNo, because the senior supplier should not be identified as a reviewer as part of the quality review technique.

How the community answered

(20 responses)
  • A
    5% (1)
  • C
    85% (17)
  • D
    10% (2)

Explanation

Explanation/Reference:

Topics