PRINCE2-PRACTITIONER · Question #165
Which project controls should be established for the Outsourcing project?
The correct answer is C. Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded. Explanation/Reference:
Progress Theme
Question
Which project controls should be established for the Outsourcing project?
Options
- AHighlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded.
- BHighlight Reports to the Project Board; Exception Reports to corporate management when stage tolerances are forecast to be exceeded.
- CHighlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded.
How the community answered
(28 responses)- A7% (2)
- B7% (2)
- C86% (24)
Explanation
Explanation/Reference:
Topics
#project controls#Highlight Reports#Exception Reports#reporting hierarchy