PRINCE2-PRACTITIONER · Question #165

Which project controls should be established for the Outsourcing project?

The correct answer is C. Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded. Explanation/Reference:

Progress Theme

Question

Which project controls should be established for the Outsourcing project?

Options

  • AHighlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded.
  • BHighlight Reports to the Project Board; Exception Reports to corporate management when stage tolerances are forecast to be exceeded.
  • CHighlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded.

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    7% (2)
  • C
    86% (24)

Explanation

Explanation/Reference:

Topics

#project controls#Highlight Reports#Exception Reports#reporting hierarchy