Question

Which project controls should be established for the Outsourcing project?

Options

  • AHighlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded.
  • BHighlight Reports to the Project Board; Exception Reports to corporate management when stage tolerances are forecast to be exceeded.
  • CHighlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded.