PRINCE2
PRINCE2-PRACTITIONER · Question #162
While preparing the Risk Management Strategy, the Project Manager considered the commercial customer/supplier environment and how this may affect the management of risk. Which approach should the…
The correct answer is C. Due to the sensitive nature of this project, consideration should be given to creating a separate Risk Register to be held by MFH and the selected supplier. Explanation/Reference:
Risk Theme
Question
While preparing the Risk Management Strategy, the Project Manager considered the commercial customer/supplier environment and how this may affect the management of risk. Which approach should the Outsourcing project adopt?
Options
- APlan to use the selected service provider's risk management procedures.
- BAll project risks associated with the specialist deliverables should be owned by the selected service provider.
- CDue to the sensitive nature of this project, consideration should be given to creating a separate Risk Register to be held by MFH and the selected supplier.
How the community answered
(30 responses)- A17% (5)
- B7% (2)
- C77% (23)
Explanation
Explanation/Reference:
Topics
#Risk Management Strategy#Risk Register#commercial environment#supplier risk
Community Discussion
No community discussion yet for this question.