nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #274

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there…

The correct answer is C. No, because risks responses should be identified as part of the 'plan' step. Explanation/Reference:

Risk Theme

Question

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.'' In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e- learning course' whenever a part of the 'classroom-based training materials' gains accreditation''. Is this appropriate, and why?

Options

  • AYes, because delivering incrementally will reduce the impact of the threat.
  • BYes, because a risk response needs to be implemented for this major threat.
  • CNo, because risks responses should be identified as part of the 'plan' step.
  • DNo, because a risk action should be allocated to implement a response.

How the community answered

(36 responses)
  • A
    11% (4)
  • B
    6% (2)
  • C
    81% (29)
  • D
    3% (1)

Explanation

Explanation/Reference:

Topics

#risk management procedure#plan step#implement step#risk response

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice