PRINCE2-PRACTITIONER · Question #274
The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there…
The correct answer is C. No, because risks responses should be identified as part of the 'plan' step. Explanation/Reference:
Question
The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.'' In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e- learning course' whenever a part of the 'classroom-based training materials' gains accreditation''. Is this appropriate, and why?
Options
- AYes, because delivering incrementally will reduce the impact of the threat.
- BYes, because a risk response needs to be implemented for this major threat.
- CNo, because risks responses should be identified as part of the 'plan' step.
- DNo, because a risk action should be allocated to implement a response.
How the community answered
(36 responses)- A11% (4)
- B6% (2)
- C81% (29)
- D3% (1)
Explanation
Explanation/Reference: