PRINCE2-PRACTITIONER · Question #273
PRINCE2-PRACTITIONER Question #273: Real Exam Question with Answer & Explanation
The correct answer is A. Yes, because the project registers should be tailored to meet the needs of the organization.. Explanation/Reference:
Question
During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages. Is this appropriate for a risk register, and why?
Options
- AYes, because the project registers should be tailored to meet the needs of the organization.
- BYes, because risks are often identified as a result of issues being raised.
- CNo, because an integrated project register should include the quality register as well.
- DNo, because assumptions and dependencies are sources of risk.
Explanation
Explanation/Reference: