PRINCE2-PRACTITIONER · Question #273

PRINCE2-PRACTITIONER Question #273: Real Exam Question with Answer & Explanation

The correct answer is A. Yes, because the project registers should be tailored to meet the needs of the organization.. Explanation/Reference:

Question

During previous projects, stakeholders became confused when using a number of separate project registers. Therefore, when preparing the risk management approach, the project manager created a risk register template and added it to an integrated project register. This register is a spreadsheet that includes project assumptions, issues, dependencies, and now risks, on separate pages. Is this appropriate for a risk register, and why?

Options

  • AYes, because the project registers should be tailored to meet the needs of the organization.
  • BYes, because risks are often identified as a result of issues being raised.
  • CNo, because an integrated project register should include the quality register as well.
  • DNo, because assumptions and dependencies are sources of risk.

Explanation

Explanation/Reference: