While capturing previous lessons, the Project Manager discovered several interesting facts about outsourcing. Which fact is an appropriate lesson for the Outsourcing project?
The correct answer is C. Contracts with service providers should include the timescale within which readiness for service is expected following the transfer of equipment and staff. Explanation/Reference:
Starting Up a Project
Question
While capturing previous lessons, the Project Manager discovered several interesting facts about outsourcing. Which fact is an appropriate lesson for the Outsourcing project?
Options
- AOutsourcing is a growth industry and is being implemented by many private sector organizations.
- BFour other government departments are also considering outsourcing some of their business functions next year.
- CContracts with service providers should include the timescale within which readiness for service is expected following the transfer of equipment and staff.
How the community answered
(29 responses)- A17% (5)
- B10% (3)
- C72% (21)
Explanation
Explanation/Reference:
Topics
#Lessons Log#previous lessons#supplier contracts#organizational learning