PRINCE2-PRACTITIONER · Question #154
Which statement is an appropriate entry for the Lessons Log?
The correct answer is B. Based on feedback from other government departments, the Ministry of Trade and Industry has provided the names of two outsourcing companies that are. Explanation/Reference:
Starting Up a Project
Question
Which statement is an appropriate entry for the Lessons Log?
Options
- AThis is the first time that the Ministry of Food Hygiene (MFH) has been involved in outsourcing.
- BBased on feedback from other government departments, the Ministry of Trade and Industry has provided the names of two outsourcing companies that are
- CThe feasibility study estimated that the outsourcing project would take two years to complete.
- DOnly the Information Technology Division and Facilities Division will be outsourced.
How the community answered
(38 responses)- A3% (1)
- B82% (31)
- C5% (2)
- D11% (4)
Explanation
Explanation/Reference:
Topics
#Lessons Log#organizational learning#previous lessons#Starting Up a Project