PRINCE2-PRACTITIONER · Question #136
Starting Up a project is triggered by which of the following?
The correct answer is D. Mandate. Explanation/Reference:
Starting Up a Project
Question
Starting Up a project is triggered by which of the following?
Options
- ALegislation
- BCorporate Strategy
- CRisks
- DMandate
How the community answered
(33 responses)- A15% (5)
- B3% (1)
- C6% (2)
- D76% (25)
Explanation
Explanation/Reference:
Topics
#project mandate#Starting Up a Project#process triggers#PRINCE2 processes