nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #133

Introductory Info Scenario: Techniques, processes and procedures 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements 2. Work is to start at the…

The correct answer is A. Delete entry 12 because this should be the Team Plan not the Stage Plan. B. A suitable entry for Extracts or references would be 'Product Descriptions are available from Project Support'. Explanation/Reference:

Managing Product Delivery

Question

Introductory Info Scenario: Techniques, processes and procedures 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements 2. Work is to start at the beginning of week 2 (Stage 4). 3. The project will take two years to complete, at an estimated cost of ?.5m. Tolerances 4. None. Constraints 5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment. 6. Installation work must take place during MFH normal working hours. 7. + £10,000 / - £25,000. Reporting arrangements 8. Highlight Report every Monday by 10.00 am. 9. The report must contain a summary of all products worked on during the previous week. 10. Project Manager must be notified of any issues immediately by telephone. Problem handling and escalation 11. Impact analysis of all issues must be completed within 24 hours. Extracts or references 12. The Stage Plan for stage 4 is available from Project Support. Approval method 13. Project Assurance will review the completed Work Package and confirm completion. Which 2 statements apply to either the Extracts or references or Approval method sections?

Options

  • ADelete entry 12 because this should be the Team Plan not the Stage Plan.
  • BA suitable entry for Extracts or references would be 'Product Descriptions are available from Project Support'.
  • CMove entry 13 to Reporting arrangements because this describes how completion will be advised to the
  • DProject Manager.
  • EDelete entry 13 because this is NOT a Project Assurance responsibility.
  • FAdd 'The Project Manager is to be advised of completion of the Work Package by email'.

How the community answered

(27 responses)
  • A
    70% (19)
  • C
    4% (1)
  • D
    4% (1)
  • E
    15% (4)
  • F
    7% (2)

Explanation

Explanation/Reference:

Topics

#Work Package#reporting arrangements#Project Assurance#configuration management

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice