Question
Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%. Which 2 actions should the Team Manager take in response to this situation?
Options
- ACheck the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.
- BUpdate the Team Plan by increasing all future work estimates by 10%.
- CAmend the Work Package and ensure that the revised targets are met.
- DEscalate the situation in the next Checkpoint Report.
- ERaise an issue that costs will exceed tolerance if the current trend continues.