PRINCE2-PRACTITIONER · Question #175
Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed…
The correct answer is A. Check the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing. E. Raise an issue that costs will exceed tolerance if the current trend continues. Explanation/Reference:
Managing Product Delivery
Question
Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%. Which 2 actions should the Team Manager take in response to this situation?
Options
- ACheck the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.
- BUpdate the Team Plan by increasing all future work estimates by 10%.
- CAmend the Work Package and ensure that the revised targets are met.
- DEscalate the situation in the next Checkpoint Report.
- ERaise an issue that costs will exceed tolerance if the current trend continues.
How the community answered
(31 responses)- A84% (26)
- B6% (2)
- C3% (1)
- D6% (2)
Explanation
Explanation/Reference:
Topics
#Issue management#tolerance#Checkpoint Report#Work Package monitoring