nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #197

PRINCE2-PRACTITIONER Question #197: Real Exam Question with Answer & Explanation

The correct answer is C. Configuration Librarian. Explanation/Reference:

Question

Who might receive completed products before the Team Manager reports that the Work Package has been completed?

Options

  • AThe Customer
  • BThe User
  • CConfiguration Librarian
  • DThe Project Board

Explanation

Explanation/Reference:

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice