PRINCE2
PRINCE2-PRACTITIONER · Question #197
PRINCE2-PRACTITIONER Question #197: Real Exam Question with Answer & Explanation
The correct answer is C. Configuration Librarian. Explanation/Reference:
Question
Who might receive completed products before the Team Manager reports that the Work Package has been completed?
Options
- AThe Customer
- BThe User
- CConfiguration Librarian
- DThe Project Board
Explanation
Explanation/Reference:
Community Discussion
No community discussion yet for this question.