Who might receive completed products before the Team Manager reports that the Work Package has been completed?

The correct answer is C. Configuration Librarian. Explanation/Reference:

Managing Product Delivery

Question

Who might receive completed products before the Team Manager reports that the Work Package has been completed?

Options

  • AThe Customer
  • BThe User
  • CConfiguration Librarian
  • DThe Project Board

How the community answered

(36 responses)
  • A
    11% (4)
  • B
    6% (2)
  • C
    81% (29)
  • D
    3% (1)

Explanation

Explanation/Reference:

Topics

#Configuration Librarian#Work Package completion#product handover#Managing Product Delivery