PRINCE2
PRINCE2-PRACTITIONER · Question #176
The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate…
The correct answer is B. Check the Product Descriptions to ascertain who should have approved the products. D. Check the approval records as required in the Work Package. Explanation/Reference:
Managing Product Delivery
Question
The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people. Which 2 actions should the Team Manager take to check that the completed products have been approved as required?
Options
- ACheck the Work Package to ascertain who should approve the completed Work Package.
- BCheck the Product Descriptions to ascertain who should have approved the products.
- CCheck the Configuration Management Strategy for product handover procedures.
- DCheck the approval records as required in the Work Package.
- ECheck the Product Descriptions for the quality method required.
How the community answered
(24 responses)- A4% (1)
- B83% (20)
- C4% (1)
- E8% (2)
Explanation
Explanation/Reference:
Topics
#Product Descriptions#quality approval#Work Package#configuration management