PRINCE2
PRINCE2-PRACTITIONER · Question #173
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable. Which 2 actions should the…
The correct answer is B. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. C. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers. Explanation/Reference:
Managing Product Delivery
Question
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable. Which 2 actions should the Team Manager take in response to this situation?
Options
- AConsult the Senior Supplier to assign suitable reviewers.
- BDiscuss the situation with Project Assurance and agree the changes or additions to the reviewers.
- CEnsure the Quality Register is updated with details of the agreed amendments to the reviewers.
- DNotify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.
How the community answered
(46 responses)- A4% (2)
- B85% (39)
- D11% (5)
Explanation
Explanation/Reference:
Topics
#Quality Register#Work Package#Team Plan#Project Assurance
Community Discussion
No community discussion yet for this question.