During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
The correct answer is B. Checkpoint Report. Explanation/Reference:
Managing Product Delivery
Question
During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
Options
- AHighlight report
- BCheckpoint Report
- CIssue Report
- DEnd Stage Report
How the community answered
(17 responses)- A6% (1)
- B82% (14)
- C12% (2)
Explanation
Explanation/Reference: