During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

The correct answer is B. Checkpoint Report. Explanation/Reference:

Managing Product Delivery

Question

During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

Options

  • AHighlight report
  • BCheckpoint Report
  • CIssue Report
  • DEnd Stage Report

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    82% (14)
  • C
    12% (2)

Explanation

Explanation/Reference:

Topics

#Checkpoint Report#Work Package#Team Manager reporting#Managing Product Delivery