PRINCE2-PRACTITIONER · Question #174

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take…

The correct answer is C. Raise an issue explaining that tolerances are forecast to be exceeded. E. Ensure that the Quality Register is updated with the quality review result. See the full explanation below for the reasoning.

Question

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance. Which 2 actions should the Team Manager take in response to this situation?

Options

  • AAsk the reviewers to work overtime to prevent the delay.
  • BEnsure that the situation is included in the next Highlight Report.
  • CRaise an issue explaining that tolerances are forecast to be exceeded.
  • DAdvise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  • EEnsure that the Quality Register is updated with the quality review result.

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    17% (5)
  • C
    69% (20)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.