PRINCE2-PRACTITIONER · Question #174
PRINCE2-PRACTITIONER Question #174: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #174. The question stem and answer options stay visible for context.
Question
The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance. Which 2 actions should the Team Manager take in response to this situation?
Options
- AAsk the reviewers to work overtime to prevent the delay.
- BEnsure that the situation is included in the next Highlight Report.
- CRaise an issue explaining that tolerances are forecast to be exceeded.
- DAdvise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
- EEnsure that the Quality Register is updated with the quality review result.
Unlock PRINCE2-PRACTITIONER to see the answer
You've previewed enough free PRINCE2-PRACTITIONER questions. Unlock PRINCE2-PRACTITIONER for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.