PRINCE2-PRACTITIONER · Question #137
Who is responsible for appointing the Project Manager?
The correct answer is C. The Executive. Explanation/Reference:
Organization
Question
Who is responsible for appointing the Project Manager?
Options
- ACorporate or Programme Management
- BThe Project Board
- CThe Executive
- DProject Assurance
How the community answered
(29 responses)- A7% (2)
- B17% (5)
- C72% (21)
- D3% (1)
Explanation
Explanation/Reference:
Topics
#Executive role#Project Manager appointment#roles and responsibilities#Organization theme