PRINCE2-PRACTITIONER · Question #137

Who is responsible for appointing the Project Manager?

The correct answer is C. The Executive. Explanation/Reference:

Organization

Question

Who is responsible for appointing the Project Manager?

Options

  • ACorporate or Programme Management
  • BThe Project Board
  • CThe Executive
  • DProject Assurance

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    17% (5)
  • C
    72% (21)
  • D
    3% (1)

Explanation

Explanation/Reference:

Topics

#Executive role#Project Manager appointment#roles and responsibilities#Organization theme

Community Discussion

No community discussion yet for this question.