PRINCE2-PRACTITIONER · Question #80

Who is responsible for committing user resources to the project?

The correct answer is A. Senior User. Explanation/Reference:

Organization

Question

Who is responsible for committing user resources to the project?

Options

  • ASenior User
  • BSenior Supplier
  • CExecutive
  • DProject Board

How the community answered

(47 responses)
  • A
    81% (38)
  • B
    11% (5)
  • C
    6% (3)
  • D
    2% (1)

Explanation

Explanation/Reference:

Topics

#Senior User#project board roles#user resources#organization theme