Which of the following represents the four key characteristics a good Project board should display?

The correct answer is B. Authority, Credibility, Delegation, Availability. Explanation/Reference:

Organization

Question

Which of the following represents the four key characteristics a good Project board should display?

Options

  • AAuthority, Credibility, Commitment, Availability
  • BAuthority, Credibility, Delegation, Availability
  • CAuthority, Availability, Connections, Delegation
  • DAuthority, Credibility, Connections, Delegation

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    84% (43)
  • C
    6% (3)
  • D
    8% (4)

Explanation

Explanation/Reference:

Topics

#Project Board characteristics#authority#credibility#Organization