Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?

The correct answer is A. Project Assurance. Explanation/Reference:

Organization

Question

Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?

Options

  • AProject Assurance
  • BProject Manager
  • CCorporate or Programme Management
  • DProject Support

How the community answered

(44 responses)
  • A
    70% (31)
  • B
    9% (4)
  • C
    5% (2)
  • D
    16% (7)

Explanation

Explanation/Reference:

Topics

#Communication Management Strategy#Project Assurance#stakeholder communication#Organization