PRINCE2-PRACTITIONER · Question #32
Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?
The correct answer is A. Project Assurance. Explanation/Reference:
Organization
Question
Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?
Options
- AProject Assurance
- BProject Manager
- CCorporate or Programme Management
- DProject Support
How the community answered
(44 responses)- A70% (31)
- B9% (4)
- C5% (2)
- D16% (7)
Explanation
Explanation/Reference:
Topics
#Communication Management Strategy#Project Assurance#stakeholder communication#Organization
Community Discussion